Sunday, December 14, 2014

Framers


 We had 11 framers come in and start building the decks. Most of the holes had drained from the previous weekends rain.
 The wire keeps the mice out of the fiberglass which is only under the yurt floor.

They worked most of Tuesday and all of Wednesday before the rain came in. Three of the  decks have the piers cemented in.

Prepping for some Yurts

First Baptist Church of King City had some men come and help drill holes for the next few yurt decks. This happened the first two weekends of November.
They drilled 100 holes over two weekends. There were about 8 of them each weekend. Each deck has 25 piers supporting it. We did have several auger bits to choose from. We wanted the holes 12" in diameter and 30" deep.
There is a clay layer down about 12 inches that was pretty challenging. It was not present on the west side of the camping area, but the east side was a lot of work.They brought the electric jack hammer.
These pictures of from the second weekend. These men worked hard to get these holes drilled